 This
            rule applies to all motor vehicle and mobile equipment surface coating operations
            including small auto body refinishing shops. If you can demonstrate that you spray
            apply only coatings that do not contain compounds of chromium (Cr), lead (Pb), manganese
            (Mn), nickel (Ni), or cadmium (Cd) at levels above the thresholds listed in the
            federal rule, you may petition this Department and the USEPA Administrator for an
            exemption from this subpart. The petition for exemption is included in the 
                Paint Stripping & Miscellaneous Surface Coating Operations Section of
            our forms page. This rule does not apply to:
This
            rule applies to all motor vehicle and mobile equipment surface coating operations
            including small auto body refinishing shops. If you can demonstrate that you spray
            apply only coatings that do not contain compounds of chromium (Cr), lead (Pb), manganese
            (Mn), nickel (Ni), or cadmium (Cd) at levels above the thresholds listed in the
            federal rule, you may petition this Department and the USEPA Administrator for an
            exemption from this subpart. The petition for exemption is included in the 
                Paint Stripping & Miscellaneous Surface Coating Operations Section of
            our forms page. This rule does not apply to:
        
            - Surface coating performed by individuals on their personal vehicles either as a
                hobby or for maintenance or if done for others without compensation. 
- Facility maintenance. Facility maintenance does not include surface coating of motor
                vehicles, mobile equipment, or items that routinely leave and return to the facility,
                such as delivery trucks, rental equipment, or containers used to transport, deliver,
                distribute, or dispense commercial products to customers, such as compressed gas
                canisters.
            How Do I Comply?
        
            You must complete and submit an Initial Notification Form
                IN and Notification of Compliance Status Form NOC-ME
            to the USEPA and this Department. You must also follow management practices and
            training requirements outlined below.
        
            Management Practices:
        
            - You must apply coatings with a high volume, low pressure (HVLP) spray gun, electrostatic
                application, airless spray gun, or air-assisted airless spray gun. You may use an
                equivalent technology that is demonstrated by the spray gun manufacturer to achieve
                transfer efficiency comparable to one of the spray gun technologies listed above,
                and for which written approval has been obtained from the Administrator (EPA).
- All spray-applied coatings must be applied in a preparation station or spray booth.
                Prep stations and spray booths must be fully enclosed with a full roof and four
                complete walls or complete side curtains. They must be ventilated at negative pressure
                so that air is drawn into any openings in the booth walls or prep station curtains.
- The exhaust from the prep station or spray booth must be fitted with filters demonstrated
                to achieve at least 98 percent filter efficiency of paint overspray. 
- Spray guns are to be cleaned in an enclosed spray gun cleaner or by cleaning the
                disassembled gun parts by hand. No spray gun cleaning is to be performed by spraying
                solvent through the gun, creating an atomized mist. 
            Training:
        
            - All painters that spray-apply coatings must certify that they have completed training
                in techniques to minimize paint overspray.
- All spray painters at new sources must complete training no later than 180 days
                after hiring, or by July 7, 2008, whichever is later. 
- All spray painters at existing sources must complete training no later than 180
                days after hiring, or by January 9, 2011, whichever is later. 
- Initial painter training will be valid for a period of five years. Painters that
                completed training in the last five years before the compliance date will be able
                to use that training to satisfy the initial requirement. These painters must still
                renew training within five years of the initial training date. Initial training
                is not required if documentation or certification demonstrates that a painter’s
                work experience and/or training has resulted in equivalent training.
- Refresher training must be repeated at least once every five years.
- Initial and refresher training must address the following topics to reduce coating
                overspray and emissions:
                
                    - spray gun equipment selection, set up, and operation, including measuring coating
                        viscosity, selecting the proper fluid tip or nozzle, and achieving the proper spray
                        pattern, air pressure and volume, and fluid delivery rate; 
- spray technique for different types of coatings to improve transfer efficiency and
                        minimize coating usage and overspray, including maintaining the correct spray gun
                        distance and angle to the part, using proper banding and overlap, and reducing lead
                        and lag spraying at the beginning and end of each stroke; 
- routine spray booth and filter maintenance, including filter selection and installation;
                        and
- environmental compliance with the requirements of this subpart.